What is the production lead time for this geranium oil?

Lead time depends on whether you are drawing from stock or commissioning a fresh batch. Stock items are ready within days; fresh distillations follow the harvest and QC calendar. The typical working windows are below.

Lead Time Guide

ScenarioLead timeNotes
Stock batch (standard spec)3-7 daysReleased from bulk tanks, QC and packing included
Fresh distillation (harvest season)15-30 daysDepends on the harvest window and your volume
Off-season fresh distillation30-60 daysRequires stored green material or next-crop planning
Contract / dedicated lot45-60 daysIncludes capacity reservation and profile blending
Sample order2-5 daysSmall pack by courier
  • Time counted from confirmed PO and deposit; QC release (CoA) adds 2-3 working days to any scenario
  • For large volumes, order at least 30 days before your production start — QC and dangerous-goods booking are the critical path
  • If you need a specific crop year or single-origin lot, tell us in the PO so we can allocate the right stock
  • Expedited options exist for urgent stock orders — confirm availability with your sales contact first